Wednesday, July 22, 2009

Progress Continues! Monterra's Rios del Sol Phase One.

As the roads continue being developed in Phase 1 it's now time to start advancing with the water management. The rainy season will be underway soon with October having the most rain.
For the last few days trucks have been arriving on our site with our 'alcantarillas' (basically big pipes). The alcantarillas are now being installed to maintain water flows in selected areas of the rivers.

Wednesday, July 15, 2009

Monterra's Rios del Sol - Phase One Bridges.

There are 2 bridges needed for phase 1 RDS. The first bridge is at the entrance and will expand 12 meters. The second is 500 meters in the property and will expand 6 meters. The engineering and design plans for these bridges have been completed and approved. Bridge construction will begin as our roads advance and when the weather permits. In the meantime the property is still drivable without the bridges.